Excel function · Dates

DAYS

Returns the number of days between two dates.

What it does

DAYS counts the days from a start date to an end date. It gives the same result as subtracting the dates, but makes the order of the arguments clear: the end date comes first.

Syntax

=DAYS(end_date; start_date)

Arguments in square brackets are optional, and … means you can add more of the same. In this Excel language, arguments are separated by ;

Arguments

end_date
The later date.
start_date
The earlier date.

Example

A project runs from 2 March to 15 April 2026. How many days is that?

ABC
1StartEndDays
22026-03-022026-04-1544

The formula in C2:

=DAYS(B2;A2)

Result: 44

From 2 March to 31 March is 29 days, plus 15 days in April: 44.

Common mistakes

  • Putting the start date first, which gives a negative number. The end date comes first.
  • Expecting both ends to count. From Monday to Tuesday is 1 day; add 1 if you count both days.

In other Excel languages

Excel translates function names, and in some languages the argument separator too. Type the name your Excel shows.

Excel languageFunction nameSeparator
EnglishDAYS,
DeutschTAGE;
FrançaisJOURS;
Español (España)Not confirmed yet;
Español (México)Not confirmed yet,
日本語DAYS,
한국어DAYS,
繁體中文DAYS,
ไทยDAYS,
ខ្មែរDAYS,
Tiếng ViệtDAYS;

Practise it

More from this module

All functions